Sun Galaxy Complex officially broke ground on 25 July 2026 in Ngu Hanh Son ward, Da Nang, with an announced total investment of nearly VND 10,750 billion. This page tracks what is independently verifiable about the project's current construction stage, the planning approvals that came before it, and — with clear caveats — what a realistic completion timeline looks like.
Groundbreaking on 25 July 2026
Sun Group held the official groundbreaking ceremony for Sun Galaxy Complex on 25 July 2026. Beyond the developer's own announcement, the event was independently reported by Sài Gòn Giải Phóng, a state-run newspaper unaffiliated with the developer, which named the project directly and put the announced investment value at nearly VND 10,750 billion. Groundbreaking marks the point where the project moved from approved paperwork and drawings into physical construction on site.
For a wider due-diligence check on the developer and operator themselves — Sun Group's track record, Accor's operating role, and how we corroborate the developer's own claims against independent press — see our developer & operator guide.
Planning Approval Timeline, Before Groundbreaking
Groundbreaking did not happen in isolation — it followed a documented planning approval process. The Da Nang People's Committee approved the project's revised 1/500 detailed masterplan under Decision 1415/QĐ-UBND, dated 29 April 2025, publicly disclosed on the city government portal on 21 July 2025. Groundbreaking followed on 25 July 2026, roughly a year after public disclosure of the approved plan.
This sequence — approval, public disclosure, then groundbreaking — is the standard basis for checking a project's legal footing before construction starts. Full detail on the underlying planning decision, in Vietnamese, is available at galaxycomplexdanang.vn/sun-galaxy-complex-quy-hoach-1-500/; see our legal status page for the English-language summary and pre-transaction document checklist.
360° Virtual Site Tour
Follow the current state of the Sun Galaxy Complex construction site through the 360° virtual tour below, the same tour embedded on our homepage.
Current Stage and Expected Timeline
As of this page's last update, Sun Galaxy Complex is in early-stage construction following the 25 July 2026 groundbreaking. Sun Group has not published an official handover date. Based on a typical construction period of around 36 months for a project of this scale, our distribution team's internal working estimate places completion and handover around 2028.
Treat this 2028 figure carefully: it is an internal estimate from the sales/distribution side, not an official commitment or published schedule from Sun Group. We will update this page if and when the developer publishes a confirmed handover date — until then, confirm the current estimate directly with our team before relying on it for any time-sensitive decision.
How to Assess Progress Independently
The most reliable way to track progress in practice is not to read progress announcements at face value, but to compare what is physically built on site against what the approved masterplan said would be built — the grandstand, the open-air stage, and the tower structure itself. How closely those match is a practical, independent measure of how the project is tracking.
Monthly Progress Updates
This page holds the project's foundational, evergreen progress facts — groundbreaking, investment value, and the planning timeline — and is updated in place as those facts change. Point-in-time construction developments are tracked separately in Vietnamese-language monthly updates, published in our news section whenever there is a genuine milestone worth reporting: see the August 2026 progress update (Vietnamese) for the latest. There is not yet an English-language monthly series; contact our English-speaking team directly for the latest verified status between updates.
Sources, checked 13/08/2026: groundbreaking date and investment value — Sun Group's own announcement, cross-checked against Sài Gòn Giải Phóng (25/07/2026); planning approval (Decision 1415/QĐ-UBND, 29 April 2025; public disclosure 21 July 2025) — Da Nang People's Committee, via the Da Nang city government portal. The 2028 completion estimate is an internal working estimate from our distribution team, not an official Sun Group announcement.
Frequently Asked Questions
Has Sun Galaxy Complex broken ground?
Yes. Sun Galaxy Complex officially broke ground on 25 July 2026, in Ngu Hanh Son ward, Da Nang, with an announced total investment of nearly VND 10,750 billion.
How much is the total investment in Sun Galaxy Complex?
Nearly VND 10,750 billion, as announced at the groundbreaking ceremony and independently reported by Sài Gòn Giải Phóng newspaper.
When will Sun Galaxy Complex be completed or handed over?
Sun Group has not published an official handover date. Based on a typical construction period of around 36 months for a project of this scale, our distribution team's internal working estimate places completion and handover around 2028. This is an internal estimate, not an official announcement by Sun Group, and should be treated accordingly until the developer publishes a confirmed date.
Where can I watch Sun Galaxy Complex's construction progress?
A 360° virtual site tour is embedded on this page and on the homepage. Vietnamese-language monthly progress updates are also published in our news section when there is a genuine construction milestone to report; there is not yet an English-language monthly series.
How was Sun Galaxy Complex's planning approved before construction started?
The Da Nang People's Committee approved the project's revised 1/500 detailed masterplan under Decision 1415/QĐ-UBND on 29 April 2025, and the dossier was publicly disclosed on 21 July 2025 — both ahead of the 25 July 2026 groundbreaking.